Relative Rates Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answers to the nearest tenth of a day.


When Tammy and Mark work together to complete a job it takes them 12 days. However, when Mark works alone, it takes 6 days longer than when Tammy works alone.

How long would it take Tammy and Mark to do the job if each of them works alone?


Tammy's solo rate is days.
Mark's solo rate is days.