Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a week.


Frank can do a certain job in 7 weeks. Shawna can do the same job in 5 weeks.

Frank and Shawna work together to complete the same job. However, Frank starts working 4 weeks after Shawna starts to work. How many weeks will it take for them to complete the job once Shawna starts to work?


weeks