Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Leslie can do a certain job in 5 weeks. Sue can do the same job in 6 weeks.Leslie and Sue work together to complete the same job. However, Leslie starts working 2 weeks after Sue starts to work. How many weeks will it take for them to complete the job once Sue starts to work? weeks
Leslie can do a certain job in 5 weeks. Sue can do the same job in 6 weeks.Leslie and Sue work together to complete the same job. However, Leslie starts working 2 weeks after Sue starts to work. How many weeks will it take for them to complete the job once Sue starts to work?