Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Sue can do a certain job in 7 months. George can do the same job in 6 months.Sue and George work together to complete the same job. However, Sue starts working 1 months after George starts to work. How many months will it take for them to complete the job once George starts to work? months
Sue can do a certain job in 7 months. George can do the same job in 6 months.Sue and George work together to complete the same job. However, Sue starts working 1 months after George starts to work. How many months will it take for them to complete the job once George starts to work?