Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a week.


Leslie can do a certain job in 5 weeks. George can do the same job in 8 weeks.

Leslie and George work together to complete the same job. However, Leslie starts working 2 weeks after George starts to work. How many weeks will it take for them to complete the job once George starts to work?


weeks