Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Juanita can do a certain job in 10 days. Alice can do the same job in 8 days.Juanita and Alice work together to complete the same job. However, Juanita starts working 2 days after Alice starts to work. How many days will it take for them to complete the job once Alice starts to work? days
Juanita can do a certain job in 10 days. Alice can do the same job in 8 days.Juanita and Alice work together to complete the same job. However, Juanita starts working 2 days after Alice starts to work. How many days will it take for them to complete the job once Alice starts to work?