Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Mark can do a certain job in 6 weeks. Shawna can do the same job in 9 weeks.Mark and Shawna work together to complete the same job. However, Mark starts working 4 weeks after Shawna starts to work. How many weeks will it take for them to complete the job once Shawna starts to work? weeks
Mark can do a certain job in 6 weeks. Shawna can do the same job in 9 weeks.Mark and Shawna work together to complete the same job. However, Mark starts working 4 weeks after Shawna starts to work. How many weeks will it take for them to complete the job once Shawna starts to work?