Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Frank can do a certain job in 11 days. Petra can do the same job in 6 days.Frank and Petra work together to complete the same job. However, Frank starts working 1 days after Petra starts to work. How many days will it take for them to complete the job once Petra starts to work? days
Frank can do a certain job in 11 days. Petra can do the same job in 6 days.Frank and Petra work together to complete the same job. However, Frank starts working 1 days after Petra starts to work. How many days will it take for them to complete the job once Petra starts to work?