Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a month.


Leslie can do a certain job in 10 months. Juanita can do the same job in 9 months.

Leslie and Juanita work together to complete the same job. However, Leslie starts working 3 months after Juanita starts to work. How many months will it take for them to complete the job once Juanita starts to work?


months