Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. George can do a certain job in 11 months. Sue can do the same job in 7 months.George and Sue work together to complete the same job. However, George starts working 4 months after Sue starts to work. How many months will it take for them to complete the job once Sue starts to work? months
George can do a certain job in 11 months. Sue can do the same job in 7 months.George and Sue work together to complete the same job. However, George starts working 4 months after Sue starts to work. How many months will it take for them to complete the job once Sue starts to work?