Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. George can do a certain job in 6 months. Petra can do the same job in 9 months.George and Petra work together to complete the same job. However, George starts working 5 months after Petra starts to work. How many months will it take for them to complete the job once Petra starts to work? months
George can do a certain job in 6 months. Petra can do the same job in 9 months.George and Petra work together to complete the same job. However, George starts working 5 months after Petra starts to work. How many months will it take for them to complete the job once Petra starts to work?