Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Frank can do a certain job in 10 months. Leslie can do the same job in 6 months.Frank and Leslie work together to complete the same job. However, Frank starts working 2 months after Leslie starts to work. How many months will it take for them to complete the job once Leslie starts to work? months
Frank can do a certain job in 10 months. Leslie can do the same job in 6 months.Frank and Leslie work together to complete the same job. However, Frank starts working 2 months after Leslie starts to work. How many months will it take for them to complete the job once Leslie starts to work?