Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a week.


Robert can do a certain job in 6 weeks. Mary can do the same job in 5 weeks.

Robert and Mary work together to complete the same job. However, Robert starts working 2 weeks after Mary starts to work. How many weeks will it take for them to complete the job once Mary starts to work?