Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Alone, Robert can do a certain job in 23 weeks. When Robert and Joe work together, they can finish the same job in 7 weeks.How long would it take Joe to do the job alone? weeks
Answer the following work problem. Report your answer to the nearest tenth of a week.
Alone, Robert can do a certain job in 23 weeks. When Robert and Joe work together, they can finish the same job in 7 weeks.How long would it take Joe to do the job alone?