Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a year. Alice can do a certain job in 8 years. Joe can do the same job in 10 years.Alice and Joe work together to complete the same job. However, Alice starts working 4 years after Joe starts to work. How many years will it take for them to complete the job once Joe starts to work? years
Alice can do a certain job in 8 years. Joe can do the same job in 10 years.Alice and Joe work together to complete the same job. However, Alice starts working 4 years after Joe starts to work. How many years will it take for them to complete the job once Joe starts to work?