Answer the following work problem. Report your answer to the nearest tenth of a day.


Petra can do a certain job in 10 days. Juanita can do the same job in 11 days.

Petra and Juanita work together to complete the same job. However, Petra starts working 1 days after Juanita starts to work. How many days will it take for them to complete the job once Juanita starts to work?


days