Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a year. Robert can do a certain job in 11 years. Juan can do the same job in 8 years.Robert and Juan work together to complete the same job. However, Robert starts working 4 years after Juan starts to work. How many years will it take for them to complete the job once Juan starts to work? years
Robert can do a certain job in 11 years. Juan can do the same job in 8 years.Robert and Juan work together to complete the same job. However, Robert starts working 4 years after Juan starts to work. How many years will it take for them to complete the job once Juan starts to work?