Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Leslie can do a certain job in 6 weeks. Kris can do the same job in 5 weeks.Leslie and Kris work together to complete the same job. However, Leslie starts working 3 weeks after Kris starts to work. How many weeks will it take for them to complete the job once Kris starts to work? weeks
Leslie can do a certain job in 6 weeks. Kris can do the same job in 5 weeks.Leslie and Kris work together to complete the same job. However, Leslie starts working 3 weeks after Kris starts to work. How many weeks will it take for them to complete the job once Kris starts to work?