Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Shawna can do a certain job in 10 months. Juanita can do the same job in 8 months.Shawna and Juanita work together to complete the same job. However, Shawna starts working 2 months after Juanita starts to work. How many months will it take for them to complete the job once Juanita starts to work? months
Shawna can do a certain job in 10 months. Juanita can do the same job in 8 months.Shawna and Juanita work together to complete the same job. However, Shawna starts working 2 months after Juanita starts to work. How many months will it take for them to complete the job once Juanita starts to work?