Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a hour.


Shawna can do a certain job in 10 hours. Joe can do the same job in 11 hours.

Shawna and Joe work together to complete the same job. However, Shawna starts working 4 hours after Joe starts to work. How many hours will it take for them to complete the job once Joe starts to work?


hours