Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated April 7th, 2019

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a day.


Lee can do a certain job in 5 days. Robert can do the same job in 7 days.

Lee and Robert work together to complete the same job. However, Lee starts working 4 days after Robert starts to work. How many days will it take for them to complete the job once Robert starts to work?


days