Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Leslie can do a certain job in 10 days. Maria can do the same job in 8 days.Leslie and Maria work together to complete the same job. However, Leslie starts working 4 days after Maria starts to work. How many days will it take for them to complete the job once Maria starts to work? days
Leslie can do a certain job in 10 days. Maria can do the same job in 8 days.Leslie and Maria work together to complete the same job. However, Leslie starts working 4 days after Maria starts to work. How many days will it take for them to complete the job once Maria starts to work?