Delayed Start Work Word Problems
Review the Lesson | MATHguide homepage Updated June 18th, 2023

Waiting for your answers...

Answer the following work problem. Report your answer to the nearest tenth of a day.


Juan can do a certain job in 6 days. Sue can do the same job in 5 days.

Juan and Sue work together to complete the same job. However, Juan starts working 1 days after Sue starts to work. How many days will it take for them to complete the job once Sue starts to work?


days