Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a day. Thadeus can do a certain job in 10 days. Mark can do the same job in 8 days.Thadeus and Mark work together to complete the same job. However, Thadeus starts working 1 days after Mark starts to work. How many days will it take for them to complete the job once Mark starts to work? days
Thadeus can do a certain job in 10 days. Mark can do the same job in 8 days.Thadeus and Mark work together to complete the same job. However, Thadeus starts working 1 days after Mark starts to work. How many days will it take for them to complete the job once Mark starts to work?