Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a month. Leslie can do a certain job in 11 months. Joe can do the same job in 7 months.Leslie and Joe work together to complete the same job. However, Leslie starts working 4 months after Joe starts to work. How many months will it take for them to complete the job once Joe starts to work? months
Leslie can do a certain job in 11 months. Joe can do the same job in 7 months.Leslie and Joe work together to complete the same job. However, Leslie starts working 4 months after Joe starts to work. How many months will it take for them to complete the job once Joe starts to work?