Waiting for your answers... Answer the following work problem. Report your answer to the nearest tenth of a week. Leslie can do a certain job in 7 weeks. Shawna can do the same job in 11 weeks.Leslie and Shawna work together to complete the same job. However, Leslie starts working 3 weeks after Shawna starts to work. How many weeks will it take for them to complete the job once Shawna starts to work? weeks
Leslie can do a certain job in 7 weeks. Shawna can do the same job in 11 weeks.Leslie and Shawna work together to complete the same job. However, Leslie starts working 3 weeks after Shawna starts to work. How many weeks will it take for them to complete the job once Shawna starts to work?